Lap Pool Redevelopment Project
Get ready to swim in the new 50m lap pool!
0
months
0
days
0
hours
Construction of the new lap pool at Arena Joondalup is scheduled to begin in December 2024 with the project expected to take approximately 12 months and open in early 2026.
Keep an eye on this page and our social media channels for the latest updates on the progress of the project and to get any alerts on how the project may impact your visit to the venue.
Please note construction traffic and noise may be present when visiting the venue through the duration of the project.
With the support of the WA Government, construction on a brand new 50m lap pool is about to commence that will service the northern suburbs for decades to come.
This multi-million dollar project will bring several upgrades and features to Arena Joondalup, including:
As well as the time required to fill the pool and to test the new equipment, public health and safety regulations require at least five weeks to fill the pool and subsequent commissioning, water testing and approvals.
This is why the pool is expected to open in February of 2026 despite the projected completion of the project by the end of 2025.
The pool will be 1.35m deep at the Eastern end with the ramp and stair access, to 2m deep at the Western end.
The total water volume of the new pool will be approximately 2000m3 (or 2 million litres) which is similar (slightly more) than the former pool.
The updated changerooms ensure the facility meets current standards for compliance, best practices, and accessibility. The addition of a compliant adult Changing Rooms facility and upgraded Universal Access Toilets (UAT) offers greater independence to users with disabilities or mobility challenges, including the elderly, parents with prams, and anyone needing extra support.
These accessible facilities are designed with features such as handrails, accessible basins, and wider doorways to accommodate wheelchair access. Additionally, larger toilet spaces are equipped with accessible fixtures, including lower sink heights, hands-free taps, reachable soap dispensers, and emergency assistance buttons within easy reach.